INE 445 Midterm, Spring 2014
Lebanese American University · Project Management · 14 pages
Showing the first 10 of 14 pages. Download the PDF to see all of it.
Show the text of this exam
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
1 of 6
NAME:_______________________________
SCORE:___________
This is a 75 min closed book exam.
Problem 1: (25%)
The P-H Microship Co. needs to undertake a major maintenance and renovation program
to overhaul and modernize its facilities for wafer fabrication. The company’s president is
planning the schedule for this project and has identified five major activities that will
need to be performed according to the following project network.
He also has gathered the following data about the normal point and crash point for each
of these activities.
Activity
Normal Time
(weeks)
Crash Time
(weeks)
Normal Cost
(x1000)
Crash Cost
(x1000)
A
3
2
54
60
B
4
3
62
65
C
5
2
66
70
D
3
1
40
43
E
4
2
75
80
A
E
C
B
D
Finish
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
2 of 6
These costs reflect the company’s direct cost for the material, equipment, and direct labor
required to perform the activities. In addition, the company incurs indirect project costs
such as supervision and other customary overhead costs, interest charges for capital tied
up and so forth. Indirect costs run at $5000 per month. He wants to minimize the overall
cost of the project. Therefore, to save some of these indirect costs, he concludes that he
should shorten the project by doing some crashing to the extent that crashing cost for
each additional week saved is less than $5000.
a) To prepare for analyzing the effect of crashing, find the earliest times, latest
times, and total float for each activity when they are done at Normal times.
Identify the corresponding critical path and project duration.
b) Use time-cost tradeoff analysis to determine which activities should be crashed
and by how much to minimize the overall cost of project. Under this plan, what
is the duration and cost of each activity? How much money is saved by doing this
crashing?
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
3 of 6
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
4 of 6
Problem 2: (20%)
For the problem data presented in problem 1, use a linear programming approach to
answer question b). Formulate the problem and show the steps you would use in deriving
the solution that minimizes overall project costs.
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
5 of 6
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
6 of 6
Problem 3: (25%)
The president of Log Construction Company is considering placing a bid on a building
project. She determined that five tasks would need to be performed to carry out the
project. Using the Pert three-estimate approach, she has obtained the estimates in the
table below for how long these tasks will take. Also shown are the precedence
relationships for these tasks.
Task
Time Required
Optimistic
estimate
Most likely
estimate
Pessimistic
estimate
Immediate
Predecessors
A
3 weeks
4 weeks
5 weeks
_
B
2 weeks
2 weeks
2 weeks
A
C
3 weeks
5 weeks
6 weeks
B
D
1 week
3 weeks
5 weeks
A
E
2 weeks
3 weeks
5 weeks
B, D
There is a penalty of $500,000 if the project is not completed in 11 weeks. Therefore
President is very interested in how likely it is that his company could finish the project in
time.
a) Construct the project network for this project
b) Find the estimate of the mean and variance of the duration of each activity
c) Find the mean and the most likely Pert critical path
d) Find the approximate probability of completing the project within 11 weeks
e) The president has concluded that the bid she would need to make to have a
realistic chance of winning the contract would earn Log Construction a profit of
about $250,000 if the project completed within 11 weeks. However because of
the penalty for missing this deadline, her company would lose about $250,000 if
the project takes more than 11 weeks. Therefore, she wants to place the bid only
if she has at least a 50% chance of meeting the deadline. How would you advise
her?
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
7 of 6
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
8 of 6
Problem 4: (20%)
For the precedence network shown below determine the missing link lags and the four
floats for each activity. Identify the critical path. Also, write the equations for computing
activity floats based on link lags.
FF = 3
FF = 5
TF = 0
Lag = 1
A
B
E
G
K
D
C
F
H
Social List – LAU Jbeil
… at your service
THE LEBANESE AMERICAN UNIVERSITY
Project Management
INE 427 - Fall 2003
MIDTERM EXAM
Dr. Pierrette Zouein
9 of 6
Problem 5: (10%)
The four vertical lines in the figure below indicate the early and late times for events i
and j. (It is assumed that the time scale extends from left to right across the page.)
Complete this figure to show early and late start and finish dates for activity (i,j). Also
show graphically and in an equation form all the various floats that can occur in a
network. The length of the arrow for activity (i,j) equals its duration (i.e., in drawing do
not assume that it is longer or shorter than shown).
Tij
TEi
TLi
TEj
TLj
Social List – LAU Jbeil
… at your service
Social List – LAU Jbeil
… at your service
Social List – LAU Jbeil
… at your service
Social List – LAU Jbeil
… at your service
Social List – LAU Jbeil
… at your service
Social List – LAU Jbeil
… at your service