ENMG 400 Problems, Spring 2008
American University of Beirut · Engineering Economy · 7 pages
More ENMG 400 files
Show the text of this problems
te
ENMG400 Assigned Problems
Chapters 1 > 9
Fag & Arch. Librar
Fall 05-06
1.9 Rate of return = (45/966)(100)
= 4.65%
1.17 Equivalent cost now: P + 0.1P = 16,000
1.1P = 16,000
P = $14,545.45
1.22 Simple: 1,000,000 = 500,000 + 500,000()(5)
i= 20% per year simple
Compound: 1,000,000 = 500,000(1 + iy
(1 +i)° =2.0000
(1 + i) = (2.0000)°?
i= 14.87%
1.39 The cash flow diagram is:
$3000
$10,000
2.9 F = 1,700,000(F/P,18%,1)
= 1,700,000(1.18)
= $2,006,000
2.31 (a) CF3 = 280,000 — 2(50,000)
= $180,000
(b) A = 280,000 — 50,000(A/G,12%,5)
= 280,000 — 50,000(1.7746)
= $191,270
2.40 For g=i, P = 60,000(0.1)[15/(1 + 0.04)]
= $86,538
2.54 400,000 = 320,000 + 50,000(A/G,i,5)
(A/G,i,5) = 1.6000
Interpolate between i = 22% and i = 24%
i= 22.6%
3.4 P = 100,000(P/A,15%,3) + 200,000(P/A, 15%,2)(P/F,15%,3)
= 100,000(2.2832) + 200,000(1.6257)(0.6575)
= $442,100
Eng, & Arch. Library
ENMG400 Assigned Problems Fall 05-06
Chapters 1 > 9
3.17 A=600(A/P,12%,5) + 4000(P/A,12%,4)(A/P,12%,5)
= 600(0.27741) + 4000(3.0373)(0.27741)
= $3536.76
3.27 Move all cash flows to year 9.
0 = -800(F/A,14%,2)(F/P, 14%,8) + 700(F/P,14%,7) + 700(F/P,14%,4)
—950(F/A, 14%,2)(F/P,14%,1) + x — 800(P/A, 14%,3)
0 = -800(2.14)2.8526) + 700(2.5023) + 700(1.6890)
—950(2.14)(1.14) + x — 800(2.3216)
x = $6124.64
4.9 i/6months = 0.14/2 = 7%
423 P = 5000(P/F,4%,16)
= 5000(0.5339)
= $2669.50
445 i =e"P_]
= 12.75%
453 P = 150,000(P/F,12%,2)(P/F,10%,3)
= 150,000(0.7972)(0.75 13)
= $89,840
5.9 PWa = -80,000 — 30,000(P/A,12%,3) + 15,000(P/F,12%,3)
= -80,000 — 30,000(2.4018) + 15,000(0.7118)
= $-141,377
5.15 PWotastic = -75,000 - 27,000(P/A,10%,6) - 75,000(P/F,10%,2)
- 75,000(P/F,10%,4)
= -75,000 - 27,000(4.3553) - 75,000(0.8264) - 75,000(0.6830)
= $-305,798
PWoatuminum = -125,000 — 12,000(P/A,10%,6) — 95,000(P/F,10%,3)
+ 30,000(P/F,10%,6)
= -125,000 — 12,000(4.3553) — 95,000(0.7513) + 30,000(0.5645)
= $-231,702
Use aluminum case
5.21 FW, = -300,000(F/P,12%,10) — 900,000(F/A, 12%,10)
= -300,000(3.1058) — 900,000(17.5487)
Eng. & Arch. Library
ENMG400 Assigned Problems Fall 05-06
Chapters 1 > 9
= $-16,725,570
FWe = -1,200,000(F/P, 12%, 10) — 200,000(F/A, 12%, 10)
— 150,000(F/A,12%,10)
= -1,200,000(3.1058) — 200,000(17.5487) — 150,000(17.5487)
= $-9,869,005
Select Plan B
5.33 CCr = [-200,000(A/P,3%,8) + 30,000 + 50,000(A/F,3%,8)]/0.03
= [-200,000(0.14246) + 30,000 + 50,000(0.11246)]/0.03
= $237,700
CCr = [-300,000(A/P,3%,16) + 10,000 + 70,000(A/F,3%, 16)}/0.03
= [-300,000(0.07961) + 10,000 + 70,000(0.04961)]/0.03
= $-347,010
CCg = -900,000 + 40,000/0.03
= $433,333
Select alternative G.
6.7 AWyx =-85,000(A/P,12%,3) — 30,000 + 40,000(A/F,12%,3)
= -85,000(0.41635) — 30,000 + 40,000(0.29635)
= $-53,536
AWy = -97,000(A/P,12%,3) — 27,000 + 48,000(A/F,12%,3)
= -97,000(0.41635) — 27,000 + 48,000(0.29635)
= $-53,161
Select robot Y by a small margin.
6.13 AWhang = -110,000(A/P,12%,3) —95,000 + 15,000(A/F,12%,3)
= -110,000(0.41635) —95,000 + 15,000(0.29635)
= $-136,353
A Wincin = -800,000(A/P,12%,6) 60,000 + 250,000(A/F,12%,6)
= -800,000(0.24323) -60,000 + 250,000(0. 12323)
= $-223,777
AWeontract = $-190,000
Use land application.
6.21 P., = 1,000,000(P/A,10%, 11) + 100,000(P/G,10%,11)
= 1,000,000(6.4951) + 100,000(26.3963)
= $9,134,730
Eng. & Arch. Libran:
ENMG400 Assigned Problems Fall 05-06
Chapters 1 > 9
Amt in yr 10 = 9,134,730(F/P,10%,11)
= 9,134,730(2.8531)
= $26,062,298
AW = 26,062,298(0.10)
= $2,606,230
7.8 0=-130,000 —49,000(P/A,i%,8) + 78,000(P/A,i%,8) + 1000(P/G,i%,8)
+ 23,000(P/F.i%,8)
Solve by trial and error or Excel
i=19.2% (Excel)
7.11 (a) 0 = -(220,000 + 15,000 + 76,000)(A/P,i%,36) + 12,000(2.00 - 1.05) + 2000
+ 100,000(A/F,i%,36)
0 = -(311,000)(A/P,i%,36) + 13,400 + 100,000(A/F,i%,36)
Solve by trial and error or Excel
i= 3.3% per month (Excel)
(b) Nominal per year = 3.3(12)
= 39.6% per year
Effective per year = (1 + 0.396/12)!? — 1
= 47.6% per year
7.26 (a) There are two sign changes, indicating that there may be two real-number
rate of return values.
(b) 0 = -30,000 + 20,000(P/F,i%,1) + 15,000(P/F,i%,2) - 2000(P/F,i%,3)
Solve by trial and error or Excel
i= 7.43% per year (Excel)
7.33, Apply net reinvestment procedure.
Fo = 3000 Fo > 0; use c
F, = 3000(1 + 0.14) - 2000
= 1420 F, > 0; use c
F, = 1420(1 + 0.14) + 1000
= 2618.80 F, > 0; usec
F3 = 2618.80(1 + 0.14) ~ 6000
= -3014.57 F3 < 0; use i’
Fy = -3014.57(1 +i’) + 3800
Set F, = 0 and solve for i’.
0 =-3014.57(1 +i’) + 3800
i? = 26.1%
ENMG400 Assigned Problems Eng. & Arch. Library Fall 05-06
Chapters 1 > 9
7.37 (a) i=5,000,000(0.06)/4 = $75,000 per quarter
After brokerage fees, the City got $4,500,000. However, before brokerage
fees, the ROR equation from the City’s standpoint is:
0 = 4,600,000 — 75,000(P/A,i%, 120) - 5,000,000(P/F,i%, 120)
Solve for i by trial and error or Excel
i= 1.65% per quarter (Excel)
(b) Nominal i per year = 1.65(4)
= 6.6% per year
Effective i per year = (1 + 0.066/4)' —1
= 6.77% per year
8.16 0=-10,000 + 1200(P/A,i,4) + 12,000(P/F,i,2) + 1000(P/F,i,4)
Solve for i by trial and error or Excel
i=30.3% (Excel)
Select machine B.
8.22 Find ROR for incremental cash flow over LCM of 4 years
0 = -50,000(A/P,i,4) + 5000 + (40,000 — 5000)(P/E, i,2)(A/P, i,4) +
2000(A/F,i,4)
Solve for i by trial and error or Excel
i=6.1% (Excel)
i< MARR; select semiautomatic machine
8.28 (a) Avs DN: 0=-30,000(A/P,i,8) + 4000 + 1000(A/F,i,8)
Solve for i by trial and error or Excel
i=2.1% (Excel)
Method A is not acceptable
B vs DN: 0 =- 36,000(A/P,i,8) + 5000 + 2000(A/F,i,8)
Solve for i by trial and error or Excel
i=3.4% (Excel)
Method B is not acceptable
C vs DN: 0 = - 41,000(A/P,i,8) + 8000 + S00(A/F,i,8)
Solve for i by trial and error or Excel
Eng. & Arch, Library
ENMG400 Assigned Problems “ — Fall 05-06
Chapters 1 > 9
i=11.3% (Excel)
Method C is acceptable
D vs DN: 0 = - 53,000(A/P,i,8) + 10,500 - 2000(A/F.i,8)
Solve for i by trial and error or Excel
i=11.1% (Excel)
Method D is acceptable
(b) A vs DN: 0 = -30,000(A/P.i,8) + 4000 + 1000(A/F,i,8)
Solve for i by trial and error or Excel
i=2.1% (Excel)
Eliminate A
B vs DN: 0 = - 36,000(A/P.i,8) + 5000 + 2000(A/F,i,8)
Solve for i by trial and error or Excel
i=3.4% (Excel)
Eliminate B
C vs DN: 0 = - 41,000(A/P,i,8) + 8000 + 500(A/F.i,8)
Solve for i by trial and error or Excel
i=11.3% (Excel)
Eliminate DN
CvsD: 0=- 12,000(A/P,i,8) + 2,500 - 2500(A/F,i,8)
Solve for i by trial and error or Excel
i=10.4% (Excel)
Eliminate D
Select method C
9.16 Convert all estimates to PW values.
PW disbenefits = 45,000(P/A,6%,15)
= 45,000(9.7122)
= $437,049
PW M&O Cost = 300,000(P/A,6%, 15)
= 300,000(9.7122)
= $2,913,660
B/C = 3,800,000 — 437.049
2,200,000 + 2,913,660
= 3,362,951/5,113,660
= 0.66
9.22 Alternative B has a larger total annual cost; it must be incrementally justified.
Use
PW values. Benefit is the difference in damage costs. For B incrementally over
A:
ENMG400 Assigned Problems Eng, & Arch, Library Fall 05-06
Chapters 1 > 9
Incr cost = (800,000 — 600,000) + (70,000 — 50,000)(P/A,8%,20)
= $200,000 + 20,000(9.8181)
= $396,362
Incr benefit = (950,000 ~ 250,000)(P/F,8%.6)
= 700,000(0.6302)
= 441,140
Incr B/C = 441,140/396,362
=1.11
Select alternative B.
9.33 Compare A to DN since it is not necessary to select one of the sites.
Avs DN
AW of Cost = 50(A/P,10%,5) + 3
= §0(0.26380) + 3
= 16.19
AW of Benefits = 20 - 0.5
=19.5
B/C = 19.5
16.19
=1.20>1.0 Eliminate DN.
BysA
AC = (90 — 50)(A/P,10%,5) + (4-3)
= 40(0.26380) + 1
= $11.552
AB = (29 - 20) — (1.5 ~ 0.5) = 8
AB/C = 8/11.552
= 0.69 < 1.0 Eliminate B.
CvsA
AC = (200 — 50)(A/P,10%,5) + (6 - 3)
= 150(0.26380) + 3
= 42,57
AB = (61 — 20) - (2.1 — 0.5) = 39.4
AB/C = 39.4/42.57
= 0,93 < 1.0 Eliminate C
Select site A