CIVE 580 Midterm, Fall 2006
American University of Beirut · Construction Management · 11 pages · Dr. Mohamed-Asme Abdul Malak
Showing the first 10 of 11 pages. Download the PDF to see all of it.
More CIVE 580 files
Show the text of this exam
1
AMERICAN UNIVERSITY OF BEIRUT
FACULTY OF ENGINEERING AND
ARCHITECTURE
CIVE 580 / ENMG 502
CONSTRUCTION MANAGEMENT
PROF. M. ASEM ABDUL-MALAK
Additional Exam Questions
January 2007
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Variant Organizational Concepts
1.
The multi-hundred-million, multi-facility Lebanese University
Complex project has been completed and made available for
occupancy only recently. The project was implemented using a
variation from the traditional approach. That is, bidding, which was
open to a number of international/regional general contracting
companies, was carried out on a partially developed design. The
A/E, a local design firm, was the party responsible for supervising
the construction contract, which got awarded to a European
general contractor. The successful general contractor opted for
substantial subcontracting, that was done on the basis of “trade” ,
with such trade works are spread in a number of facilities
throughout the project, and not on the basis of the whole works in
a “particular facility” within the project.
a)
Graph the project organizational structure adopted for the
project.
b)
Suggest a name for the adopted structure, and state the
type of the construction contract.
c)
Propose two other structures that could have been
considered by the government, one of which shall be of such
nature that would have allowed higher chances of
involvement by the local general contracting companies.
2
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Variant Organizational Concepts
1.
Answer:
a)
Adopted Organizational Structure
b)
Suggested Name: __Modified DB__ Type of Contract: ___Lump Sum___
c)
Alternate Structures
Alternative No. 1
Alternative No. 2
Owner
A/E
Int’l Contractor
Partial design and Construction
Partial design
Owner
A/E
PM
Multiple Prime Contractors
(per facility)
Owner
A/E
CM (same int’l firm)
Trade Contractors
Subcontractors
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Leading to the Go-Ahead Milestone
2.
During the pre-project planning phase:
a) The Client expects that all potential project
risks to be identified.
b) The Client expects that all potential project
risks to be resolved.
c) The Client expects that mitigation measures
for all major project risks to be formulated.
d) Any combination of the above __a & c___.
e) None of the above.
3
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Project Life Span
3.
It is correct to say that:
a) The pre-project planning and pre-construction
phases are both concluded with some form of
financial evaluation.
b) The PM firm may be involved with the owner
from as early as possible in the pre-project
phase until shortly after the completion of
construction.
c) Innovative bidding approaches and contract
types could involve giving the contractor a more
significant role during the early years of a
project’s operation phase.
d) Any combination of the above _a, b & c _.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Quantity Surveying
4.
It is correct to say that:
a)
Quantity surveying is a task undertaken during
the construction documentation stage of the
design phase.
b)
Quantity surveying is a task that contributes
very little, if any, to the administration of the
construction contract by the PM firm.
c)
Quantity surveying is never the concern of the
general contracting firm bidding for a lump sum
contract.
d)
Any combination of the above _______.
e)
None of the above.
4
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Scheduling
5.
Scheduling for the execution of
construction activities:
a)
Requires major input from the
contractor’s bid preparation team.
b)
Has an aim of graphically representing
when activities are likely to be started
and completed.
c)
Is the responsibility of the PM firm.
d)
Any combination of the above __a & b_.
e)
None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Construction Contract
6.
The construction contract:
a) Is formed following the analysis of
submitted bids.
b) Is formed following the selection of the
successful bidder.
c)
Is formed following the readiness of the
selected successful contractor to enter into
contract.
d) Any combination of the above _______.
e) None of the above.
5
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Applied Resources
7.
The applied resources:
a) Can be viewed as major indicators of the
contractor’s major areas of qualifications.
b) Are, in their majority, not re-allocable.
c)
May require major financial investments to
be made by the contractor.
d) Any combination of the above _a & c_.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Permanent Resources
8.
The procurement of permanent
resources:
a) Is contingent on the prior approval of the A/E
of the sources/suppliers of products.
b) Is the major responsibility of the contractor.
c)
May partially be handled by the owner with
the help of his CR, the PM, and/or the A/E.
d) Any combination of the above _a, b, & c_.
e) None of the above.
6
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Construction Financing
9.
Money can be viewed as an applied resource by
the contractor because:
a)
Sufficient money is required to keep the
construction wheel rolling.
b)
Progress payments made by the owner
facilitates the recycling of cash available to the
contractor through the credit facility given to
him.
c)
The owner recovers the down payment as the
construction process progresses.
d)
Any combination of the above __a & b__.
e)
None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The LS Contract
10.
When opting for a lump-sum type
contract, the Client:
a)
Strives to reduce the uncertainty inherent in
construction cost estimating.
b)
Shifts certain design-related risks to the
contractor.
c)
Attempts to relieve the PM from some of his
major responsibilities.
d)
Any combination of the above _______.
e)
None of the above.
7
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The UP Contract
11.
When opting for a unit-price type
contract, the Client:
a)
Encourages the A/E’s quantity surveying team to
be less concerned about the accuracy of
estimated quantities to be listed in the BOQ.
b)
Encourages the contractor to front-load his bid
price.
c)
Unintentionally makes room for contractors to
consider unbalancing by speculating on quantity
overrun or underrun.
d)
Any combination of the above _______.
e)
None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The C+ Contract
12.
When opting for a cost-plus type
contract, the Client:
a) May be making a compromise of not having a
fixed budget in return for definitely better
quality.
b) May be making a compromise of not having a
fixed budget in return for shorter duration.
c)
Wants to avoid having to go through a bidding
process.
d) Any combination of the above _______.
e) None of the above.
8
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Subsurface Conditions
13.
Geotechnical studies are:
a) Normally paid for by the owner, except
under a unit-price type construction
contract.
b) Commissioned by the owner, based on the
recommendations devised by the A/E in
connection with the scope of such required
studies.
c)
Required mainly when dealing with
infrastructure-type projects
d) Any combination of the above____.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Project Site Location
14.
Traffic-related studies:
a) Are a must when considering the
construction of large-scale commercial
building projects.
b) May pose difficulties causing the owner to
look for alternative locations for the
intended project.
c)
Shall be undertaken by a specialty
consultant appointed by the owner based on
the recommendation of his CR or PM.
d) Any combination of the above _a, b, & c_.
e) None of the above.
9
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Built Environment
15.
The environmental impact assessment:
a) Recommends whether the environmental
damages can be mitigated.
b) Is concerned only with the impact of the
construction process on the environment.
c)
Tackles issues of pollution to air and water
only.
d) Any combination of the above ________.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
PM’s Role
16.
Draft three Client-PM Agreement’s requirements
describing the PM’s role in analyzing the bid prices
proposed by participating bidders:
1)
The PM is to compile all proposed bids in one
comprehensive electronic document so as to
facilitate comparative analyses of received offers.
2)
The PM shall carry out the bid analysis exercise at
all levels of bid price breakdown, including overall
price, division level, and unit price level.
3)
The PM shall examine potential bid unbalancing
prior to recommending the preferred/successful
bidder to the Owner for consideration.
10
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Bid Prices Distribution
17.
Consider the distribution above:
a)
The Engineer shall be required to redesign since
only one price falls under the EE.
b)
The lowest bidder may be mistaken, and the PM
shall carefully examine the reasons behind this
price being outside the population.
c)
The lowest price is definitely unbalanced.
d)
Any combination of the above ________.
e)
None of the above.
Min Bid
Max Bid
Avg. Bid
EE
$
LS price
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Successful Bidder
18.
Consider the different distribution above, if the
owner opts to accept the price that is closest to
the average of the offered prices, the aim:
a)
May be to avoid unbalanced bids.
b)
May be to avoid dealing with claim-conscious
contractors.
c)
Is to maintain his original budget.
d)
Any combination of the above ________.
e)
None of the above.
Min Bid
Max Bid
Avg. Bid
EE
$
LS price
11
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Bidding Systems
19. Adopting a low-cost bidding
system, which incorporates an
incentive for early completion, for a
project on hand is a major step
towards entertaining the adoption
of a cost-time bidding system for
future projects.
a) True.
b) False.