CIVE 580 Midterm, Fall 2011
American University of Beirut · Construction Management · 9 pages · Dr. Mohamed-Asme Abdul Malak
More CIVE 580 files
Show the text of this exam
1
Case Study (Questions 1-4)
�
The design phase for a mid-rise building has recently being launched by a group of four
investors (the client). The building will be around forty floors, six of which will form the
substructure while the remaining 34 floors extend above the ground level forming the
g
g
g
superstructure. Only one of the investors has construction knowledge and, in fact, owns
a general contracting company. This same investor (referred to below as the fourth
investor) happens to be holding the lowest percent shares in the project. A client-
representation panel has been formed by four individual representatives delegated by
each of the four investors.
�
The client did not hire a development manager during the planning phase. The project
concept is the result of a collaborative study by two architectural offices, local and
foreign ones, selected on a competition basis by the Client. The envisioned design team
is comprised of the same two architectural offices, a foreign engineering design firm, a
local engineering design office, and a number of specialty consultants. A technical
controller will also be appointed.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
�
The client did consider the engagement of a project management firm whose first role
would have been to administer and monitor the design phase, but they ended up not
hiring one. Instead, they employed an individual to act more like a project director,
whose role is to act on behalf of the client-representation panel and to be the contact
person throughout the project implementation cycle. The fourth investor is expecting to
be given a construction management role during the construction phase. The
supervision of construction quality will be assigned to the two local architectural and
engineering offices.
Organizational Structure
1.
Draw the project’s organizational structure and state the
form(s) of contracts that could potentially be applicable for
( )
p
y
pp
the construction packages?
Client/Representation Panel/Project Director
A/E: Foreign/Local &
Sub-consultants
Design &
Supervision
Construction management
contract
CM (4th Investor)
Technical Controller
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Trade construction
contracts: lump sum,
unit price, or cost-plus
Trade
1
Trade
2
Trade
3
Trade
4
Subcontractors
2
Fourth Investor’s Involvement
2.
What roles do you envision for the fourth investor when
acting as the construction manager during the construction
acting as the construction manager during the construction
phase?
a) Facilitate the launching of all trade
contracts in harmony with design
progress.
b) Provide common logistics and support to
mall trade contractors and manage the
it
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
site.
c) Coordinate the works of all trade
contractors.
Development Manager
3.
The appointment of a development manager
3.
The appointment of a development manager
in the pre-project planning phase would
have helped the Owner in better:
a) Understanding the market needs
b) Formulating the facility’s program
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
c) Strategizing for the implementation of
the development
3
Construction Phasing
4
By opting for the phased approach as
4.
By opting for the phased approach as
implied by the case description,
a)
One can conclude that the investors are keen on
delivering the project the fast-track way.
b)
The fourth investor’s construction know-how will
inform (be of benefit to) the design process, an
advantage also expected under the design-build
approach.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
c)
The possibility of having one (or more) of the
packages being let out (awarded) on the basis of
“design-build” shall not be completely
eliminated.
Pre-Project Planning (PPP) - 1
5
I i
h
5.
It is correct to say that:
a)
The outcome of the PPP phase may be a “No-
Go” decision.
b)
A “No-Go” decision would not result in some
wasted investment by the Client.
c)
A “No-Go” decision could be the result of
technical constraints having to do with
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
technical constraints having to do with
needing to upgrade the existing
infrastructure serving the proposed project
site location and the neighboring area.
4
Pre-Project Planning (PPP) - 2
6.
It is correct to say that:
6
t s co
ect to say t at
a) For the public type project, both the
financial and economic feasibility
evaluations are needed.
b) The outcomes of the traffic and
environmental impact assessments
could influence the financial feasibility
l
ti
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
evaluation.
c) The outcomes of the development
manager’s market study feed into the
financial feasibility evaluation.
Banking Sector
7.
It is correct to say that:
a) The strengths of the banking sector in a
certain country are of interest to the
project owner.
b) The strengths of the banking sector in a
certain country are of interest to the
project prospective contractor.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
c) The same banking institution should not
end up providing financing to both the
owner and contractor of the same
project.
5
Project Manager
8.
The project manager (PM) can be
entrusted by the owner :
a) To review and interpret the value
engineering studies presented by the A/E
design firm during the pre-project planning
phase.
b) To lead, on behalf of the Owner, the bid
l
i
d
ti ti
d
th
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
analysis and negotiation process under the
design-build approach.
c) To act as the “Engineer” for the construction
contract.
Contracts/Sub-Contracts/
Trade Contracts
9
It is correct to say that the owner
9.
It is correct to say that the owner
may appoint a:
a) Project Manager (PM) to administrate
the design-build (DB) contract.
b) Construction Manager (CM) to
administrate the subcontracts under a
DB contract.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
DB contract.
c) CM to administrate the trade contracts
under the professional construction
management delivery approach.
6
Quality Assurance/Quality Control
(QA/QC)
10.
It is correct to say that:
y
a) When subcontracting firms are engaged in
projects as trade contractors, a layer of
QA/QC ends up being at least partially
compromised on.
b) The engagement of a technical controller
introduces a new layer of QA/QC in judging
the acceptability of the deliverables of the
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
p
y
A/E design consultant.
c) QA/QC is not of concern to the public owner
under the build-operate-transfer (BOT)
delivery approach.
Defects Notification Period (DNP)
11.
It is correct to say that:
y
a) The DNP is the period beyond the
substantial completion date, during which
the contractor remains fully liable for all
defects surfacing during the said period.
b) Acceptance of such liability towards this
period by the contractor comes free of
charge to the Owner.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
c) The professional construction management
approach does not pose any difficulty in
setting the DNPs for various trade
packages.
7
Bidding
Engineer’s Estimate (EE)
$ i
illi
Average Bid = 149
12.
It is correct to say that:
a)
The above distribution of received bid prices could be
interpreted as being reflective of a boom in the
construction market.
b)
The difference between the highest and lowest bids
Min Bid = 135
Max Bid= 158
$, in million
LS Price
Average Bid = 149
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
could be interpreted to indicate that the design
drawings and not the specifications may be
ambiguous.
c)
The client should definitely consider that the
bidding results are inconclusive, particularly when the
location of the EE is taken into consideration.
Quantity Surveying
13.
It is correct to say that:
y
a)
The bill of quantities (BOQ) is of significance to
the participating bidders in terms of being a
quantitative representation of the design
drawings.
b)
The bill of quantities (BOQ) is of significance to
the Project Manager in terms of facilitating the
analysis of received bid prices.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
y
p
c)
The bill of quantities (BOQ) is of significance to
the “Engineer” in terms of facilitating the
certification of payments due to the contractor
under a lump sum contract.
8
Contract Forms
14.
It is correct to say that:
)
h
l
b
l
bl
f
a) The cost-plus contract can be applicable for
the general construction contract if phased
construction is desired by the owner under
the traditional project delivery approach.
b) The unit-price contract cannot be applicable
for the multiple general construction
contracts under the multiple-prime project
delivery approach
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
delivery approach.
c) The lump sum contract cannot be applicable
for the trade construction contracts under
the professional construction management
delivery approach.
Design-Build
15.
It is correct to say that under the DB
h
approach:
a) The re-measured contract form is most
suited for the design-build contract.
b) The Client normally needs the assistance
of an A/E consultant to help prepare the
Employer’s Requirements (including the
design criteria and guidelines)
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
design criteria and guidelines).
c) The contractor could take the lead role
as the design-builder, while the design
firm is engaged through a subcontract
with (under) the contractor.
9
Acceptance of Executed Works
16.
It is correct to say that:
a)
The provisional acceptance of accomplished works by
the A/E is not necessary a prerequisite to the
certification of payment by the Project Manager acting
as the Engineer of the construction contract.
b)
The issuance of the Taking-Over Certificate by the
Engineer based on the Engineer’s determination that
the Works have been substantially completed is a
prerequisite to the start of occupancy of the built
f
l
b
h
d
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
facility by the end-users.
c)
Upon the expiry of the Defect Notification Period,
the contractor gets permanently relieved, under the
concerned Lebanese Laws, from all his liabilities
towards the integrity of the built facility.