AMERICAN UNIVERSITY OF BEIRUT
FACULTY OF ENGINEERING AND
ARCHITECTURE
CIVE 580 / ENMG 502
CONSTRUCTION MANAGEMENT
PROF. M. ASEM ABDUL-MALAK
Additional Exam Questions - 3
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Organizational Structures
1.
It is correct to say that:
a) The Client shall opt for the multiple-
prime contractors approach when the
project is LARGE.
b) The Client shall opt for the design-
build approach when the project is
COMPLEX.
c) The Client shall opt for the CM
approach when the issue of TIME is of
paramount importance to him/her.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Timing of PM Engagement
2.
It is correct to say that:
a) The Client may engage the PM soon before
the design phase is completed in
preparation for finalizing the tender
documents and launching the bidding phase.
b) The Client may engage the PM from the
onset of the project life-cycle (i.e., during
the pre-project planning).
c) Engaging the PM any earlier than the start
of construction will yield marginal benefits to
the Client.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Design-Builder
3.
It is correct to say that:
a) Phasing the D-C process is the major
determinant for selecting the design-
build approach.
b) Phasing the D-C process is a by-product
of having opted for the design-build
approach.
c) The dominance of the “D”esigner (A/E)
is not normally undermined by the
“C”onstructor under the design-build
approach.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Planning
4.
It is correct to say that:
a)
Planning for the undertaking of a construction
project by the Client will include deciding on a
project organizational structure prior to the
project go-ahead milestone.
b)
Planning for the provisioning of construction
logistics by the general contractor to support the
works implemented by subcontractors is
undertaken by the general contractor prior to
the start of construction.
c)
Architects are known for being good planners
because they have a profound understanding of
what scheduling entails.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Construction Contract Administration
5.
The role of administrating the
construction contract:
a)
Remains to be the responsibility of
the A/E when a PM is appointed,
but not when a CM is appointed.
b)
Entails dealing only with the issues
of time and cost.
c)
Entails dealing primarily with the
issues of time and cost.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Control
6.
It is correct to say that:
a) Control is exercised by the CM over
trade contractors.
b) Control is exercised by the CM over
the A/E.
c) Coordination is exercised between
the CM and the A/E.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Common Applied Resource
7.
The tower crane:
a) May represent a financial investment
difficulty for the GC on large-scale
projects, depending on the number
of cranes that will have to be
installed.
b) Can be the source of major
scheduling problems on site.
c) Is supposed to serve every spot of
the construction site.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Human Element
8.
It is correct to say that:
a)
Labor resources of various levels of experience
and skills, when available in abundance, will
lessen the burden of construction financing on the
part of the contractor.
b)
The contractor’s construction supervision team is
less critical to the construction process compared
to the A/E’s construction supervision team.
c)
The involvement of the human element in the
construction process makes room for subjectivity-
related issues that can be detrimental to the
project’s chances of success.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Heavy Construction
9.
The word “heavy”, in the title, can be used
in reference to:
a) The heavy reliance on money to keep
the construction wheel moving.
b) The size of such rock-eaters (boring
machines) as those used in tunneling
operations.
c) The size of the foundation raft for a
building tower project.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The LS Contract
10. Having selected a contractor on a
LS basis normally indicates that:
a) The Client wanted to set a firm budget
for construction.
b) The Client had insufficient confidence in
the A/E’s capabilities.
c) The Client will have no use of the bill of
quantities during the construction
phase.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The UP Contract
11.
When opting for a unit-price type
contract:
a)
The selection of the successful contractor will
basically be done in a way similar to that under
a LS type contract.
b)
The PM, in examining submitted bids, shall give
more attention to “unbalancing by front-loading”
than to “unbalancing by speculation on
quantities”.
c)
Competition is not viewed as a critical issue from
the Client’s perspective.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The C+ Contract
12.
Under a cost-plus type contract, rank the
level of difficulty, from 1(least) to
3(most), the Client will have in selecting
the successful contractor:
a) On the basis of the offered fee percentages only
(1).
b) On the basis of the offered fee percentages and
offered guaranteed maximum figures (3).
c)
On the basis of the offered fee percentages,
offered guaranteed maximum figures, and
offered savings split percentages (2).
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
A/E’s Role
13.
Draft three Client-A/E Agreement’s requirements describing
the A/E’s role in helping the Client defining the scope of
such studies and selecting the professionals with
appropriate qualifications:
1)
The Architect/Engineer shall pinpoint the studies and investigations to
be undertaken by the Owner, which are believed to be necessary for
properly designing and/or constructing the Works.
2)
The Architect/Engineer shall define the scope of such studies and
investigations, highlighting the tasks required and the deliverables to
be made.
3)
The Architect/Engineer shall advise the Owner of the names of
qualified potential individuals or entities and shall assist the Owner, if
so requested, in selecting the preferred participants.
(please confine your answer to the space provided above)
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Financial Feasibility
14.
This study:
a) Is independent from the design related
effort invested during the pre-project
planning phase.
b) Is highly dependent on how well the A/E
ends up satisfying the building’s program
functions within the total built-up area
allowed.
c) Is more important than the economic
feasibility to a consortium bidding on a
public project under the BOT approach.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Built Environment
15.
In the case of an airport project to be
constructed in a cold region, the
environmental impact assessment shall
tackle the issues of:
a) Runoff of de-icing chemicals used on
airplanes fuselage.
b) Disposal of waste including solid waste as
well as used oil, resulting from facility
operation and maintenance.
c) Noise pollution as it may affect endangered
bird species in the area.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Q&A Period
16.
It is correct to say that:
a)
Contractors, during the Q&A period, are given
more than one venue through which to inquire
about ambiguities in the design documents.
b)
Contractors, during the Q&A period, may decide
not to inquire about ambiguous design
requirements, in order to serve the purpose of
their hidden agenda, which the PM or the A/E
will likely to discover during the construction
process.
c)
Contractors, during the Q&A period, may decide
not to inquire about ambiguous design
requirements, in order to serve the purpose of
their hidden agenda, which the PM or the A/E
may get to discover during the bids evaluation
period.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Bid Prices Distribution
17.
Consider the distribution above:
a)
The maximum bid may be an indication of a
contractor with not so much work on hand.
b)
The A/E may have been conservative in
deriving to the Engineer’s Estimate.
c)
The A/E has definitely given the Client a project
that is inferior to what the Client had sought.
Min Bid
Max Bid
Avg. Bid
EE
$
LS price
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Lowest Bidder
18.
Consider the same distribution above. The owner
opted to accept the price of the lowest bidder, who
in turn declined the offer. The bid guarantee:
a)
Prevents the lowest bidder from accepting other
jobs.
b)
Will always allow the Client to bridge the full
difference between the lowest and second lowest
prices.
c)
Is a percentage of the Engineer’s estimate and is
disclosed by the Client in the bidding
documents.
Min Bid
Max Bid
Avg. Bid
EE
$
LS price