CIVE 580 Midterm, Fall 2011
American University of Beirut · Construction Management · 21 pages · Dr. Mohamed-Asme Abdul Malak
Showing the first 10 of 21 pages. Download the PDF to see all of it.
More CIVE 580 files
Show the text of this exam
AMERICAN UNIVERSITY OF BEIRUT
FACULTY OF ENGINEERING AND
ARCHITECTURE
CIVE 580 / ENMG 502
CONSTRUCTION MANAGEMENT
PROF. M. ASEM ABDUL-MALAK
Sample Exam Questions
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
A “real” case calling for your advice
1.
AUB is soon to launch a competition for the concept design of the
new building to house FEA’s engineering laboratories. The
implementation of this building within the shortest possible time
will make it possible to proceed with the rehabilitation of Bechtel
Building right afterwards. Competition is to be open to selected
international/local architectural firms. AUB is currently delivering
the SRB Project under the Design-Build approach and has adopted
the traditional approach with a PM for construction contract
administration for the HSSC and OSB Projects.
a)
Rank the project organizational structures and their
associated types of construction contract that can be
deemed viable for this new project.
b)
Clearly states the major reason that hinders the adoption
of the design-build approach.
c)
Clearly states the major reason that classifies the
adoption of the traditional approach under a cost-plus
with a GM contract as less desirable compared to other
possible approaches .
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
A “real” case calling for your advice
1.
Answer: (10 points)
a)
Organizational structures
b)
DB hindrance
c)
C+ with GM hindrance
1. CM – phased approach (LS & UP trade contracts)
2. Traditional approach (GC: C+ with a GM)
3. DB on LS basis
4. Traditional, GC on a LS or UP (with a PM from
the start of design)
How do you force a teaming-up between foreign architects
and local contractors?
Too aggressive for a non-for-profit type institution
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Go-Ahead Decision
2.
Proceeding beyond the pre-project
planning/conceptual phase:
a) Indicates that the Client has avoided
all the risks of project failure.
b) Reflects that the funds for design
development have not been secured.
c) Indicates that the project idea has
been validated.
d) Any combination of the above
________.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Interaction among Phases
3.
In relation to the design, construction,
and operation phases:
a) All phases are traditionally undertaken in a
sequential manner.
b) Design thinking is independent from
construction and operation thinking.
c) From design perspective, construction
thinking is more important than operation
thinking.
d) Any combination of the above _______.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Supervision of Construction
4.
Supervision of works execution as
exercised by the Contractor’s staff
precludes the need for an
inspection of completed works by
the supervising Architect/Engineer.
a) True.
b) False.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Role of the PM
5.
Construction contract
administration:
a)
Mainly involves dealing with time-
and cost-related issues .
b)
May involve dealing with issues
related to the quality of
accomplished works.
c)
Both of the above.
d)
None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Progress Control
6.
Control, as a function, can be
exercised effectively regardless of
the extent of planning and
scheduling undertaken.
a) True.
b) False.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
A/E versus PM
7.
Appropriating the construction
supervision functions to both an A/E
office and a PM office is meant to:
a) Avoid the inevitable partiality of the A/E.
b) Enhance the contract administration
process.
c) Facilitate communication among involved
parties.
d) Any combination of the above: b & c.
e) All of the above.
f)
None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The Phased Approach
8.
Under the appointment of a Construction
Manager (and in comparison with the
traditional project delivery approach):
a) The construction budget and duration cannot
be set.
b) The construction budget and duration cannot
normally be guaranteed.
c) Construction duration reduction is highly
possible.
d) An overall design-construction duration
reduction is highly possible.
e) Any combination of the above: b & d.
f)
All of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The DB Approach
9.
By resorting to the design-build
delivery approach, the Client can
completely avoid the appointment
of an A/E consultant and/or a PM
consultant.
a) True.
b) False.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The LS Contract
10. The lump sum contract does not
guarantee the Client the lowest
possible construction cost.
a) True.
b) False.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The UP Contract
11. The re-measured contract is
desirous to contractors since it
allows a complete shifting of
project risks to the Client.
a) True.
b) False.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
The C+ Contract
12.
The cost-plus-a-fee with a guaranteed
maximum contract resembles the lump
sum contract in that:
a) Project risks are allocated in a similar
manner.
b) The Client is, in a way, guaranteed an upper
bound for the cost of construction.
c) It gives an opportunity for the contractor to
have a higher profitability.
d) Any combination of the above _________.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Budget Control
13. The project’s construction budget is
to be maintained by the A/E
through:
a) Periodic re-estimation of cost.
b) Exercising good value engineering
practices.
c) Favoring initial cost reductions over
life-cycle considerations.
d) Any combination of the above: a & b.
e) None of the above.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Accounting for Constructability
14. Construction expertise is “best”
injected into design thinking
through:
a) The A/E’s acquired construction
knowledge.
b) The PM/CM construction background.
c) Engaging the Contractor before (or soon
after) the design phase starts.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Constructability?
15.
Observing the issue of constructability
means:
a) The design can be easily constructable.
b) The design can be economically
constructable.
c) The design drawings are deemed acceptable
in terms of the level of construction details
shown.
d) The designer is the constructor.
e) All of the above.
f)
Any combination of the above: a, b, & c.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
PM’s Role
16.
Draft four Client-PM Agreement’s requirements describing
the PM’s role in administrating the Client-A/E Agreement:
1)
The PM shall closely monitor the advancement in the
design progress achieved by the A/E with the aim of
ensuring that all interim and final milestones are met.
2)
The PM shall ensure that the A/E examine alternative
design solutions leading to the selection of systems
that are viable from a life-cycle costing perspective.
3)
The PM shall cause the A/E to undertake periodical
reviews of construction cost and review the same with
the aim of maintaining the budget set by the Client.
4)
The PM shall be responsible for reviewing all interim
and final design deliverables for completeness and
compliance with Agreement requirements.
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Engineer’s Estimate
17.
If Mean-EE > 0, then:
a) The Engineer might have under-
priced the project
b) The Engineer might have over-
priced the project
c) The Engineer has to revisit the
design
d) The Engineer has given a reasonable
estimate of construction cost
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Bid Prices Distribution
18. IF Mean-Median > 0, then:
a) There is a potential outlier at lower
end of distribution.
b) There is a potential outlier at higher
end of distribution.
c) The distribution may be symmetrical.
d) No meaningful information can be
drawn .
CIVE 580 & ENMG 502
CONSTRUCTION MANAGEMENT
Unbalancing
19. Bid unbalancing carried out on the
basis of “a speculation on quantity”
always results in bid “front-
loading”:
a) True.
b) False.
c) Not able to judge.