CIVE 580 Midterm, Fall 2011

American University of Beirut · Construction Management · 21 pages · Dr. Mohamed-Asme Abdul Malak

All CIVE 580 files
CIVE 580 Midterm, Fall 2011, page 1

Stuck on a question? A tutor can walk you through it.

CIVE 580 Midterm, Fall 2011, page 2 CIVE 580 Midterm, Fall 2011, page 3 CIVE 580 Midterm, Fall 2011, page 4 CIVE 580 Midterm, Fall 2011, page 5 CIVE 580 Midterm, Fall 2011, page 6 CIVE 580 Midterm, Fall 2011, page 7 CIVE 580 Midterm, Fall 2011, page 8 CIVE 580 Midterm, Fall 2011, page 9 CIVE 580 Midterm, Fall 2011, page 10

Showing the first 10 of 21 pages. Download the PDF to see all of it.

More CIVE 580 files

Show the text of this exam
AMERICAN UNIVERSITY OF BEIRUT FACULTY OF ENGINEERING AND ARCHITECTURE CIVE 580 / ENMG 502 CONSTRUCTION MANAGEMENT PROF. M. ASEM ABDUL-MALAK Sample Exam Questions CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT A “real” case calling for your advice 1. AUB is soon to launch a competition for the concept design of the new building to house FEA’s engineering laboratories. The implementation of this building within the shortest possible time will make it possible to proceed with the rehabilitation of Bechtel Building right afterwards. Competition is to be open to selected international/local architectural firms. AUB is currently delivering the SRB Project under the Design-Build approach and has adopted the traditional approach with a PM for construction contract administration for the HSSC and OSB Projects. a) Rank the project organizational structures and their associated types of construction contract that can be deemed viable for this new project. b) Clearly states the major reason that hinders the adoption of the design-build approach. c) Clearly states the major reason that classifies the adoption of the traditional approach under a cost-plus with a GM contract as less desirable compared to other possible approaches . CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT A “real” case calling for your advice 1. Answer: (10 points) a) Organizational structures b) DB hindrance c) C+ with GM hindrance 1. CM – phased approach (LS & UP trade contracts) 2. Traditional approach (GC: C+ with a GM) 3. DB on LS basis 4. Traditional, GC on a LS or UP (with a PM from the start of design) How do you force a teaming-up between foreign architects and local contractors? Too aggressive for a non-for-profit type institution CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The Go-Ahead Decision 2. Proceeding beyond the pre-project planning/conceptual phase: a) Indicates that the Client has avoided all the risks of project failure. b) Reflects that the funds for design development have not been secured. c) Indicates that the project idea has been validated. d) Any combination of the above ________. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Interaction among Phases 3. In relation to the design, construction, and operation phases: a) All phases are traditionally undertaken in a sequential manner. b) Design thinking is independent from construction and operation thinking. c) From design perspective, construction thinking is more important than operation thinking. d) Any combination of the above _______. e) None of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Supervision of Construction 4. Supervision of works execution as exercised by the Contractor’s staff precludes the need for an inspection of completed works by the supervising Architect/Engineer. a) True. b) False. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Role of the PM 5. Construction contract administration: a) Mainly involves dealing with time- and cost-related issues . b) May involve dealing with issues related to the quality of accomplished works. c) Both of the above. d) None of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Progress Control 6. Control, as a function, can be exercised effectively regardless of the extent of planning and scheduling undertaken. a) True. b) False. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT A/E versus PM 7. Appropriating the construction supervision functions to both an A/E office and a PM office is meant to: a) Avoid the inevitable partiality of the A/E. b) Enhance the contract administration process. c) Facilitate communication among involved parties. d) Any combination of the above: b & c. e) All of the above. f) None of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The Phased Approach 8. Under the appointment of a Construction Manager (and in comparison with the traditional project delivery approach): a) The construction budget and duration cannot be set. b) The construction budget and duration cannot normally be guaranteed. c) Construction duration reduction is highly possible. d) An overall design-construction duration reduction is highly possible. e) Any combination of the above: b & d. f) All of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The DB Approach 9. By resorting to the design-build delivery approach, the Client can completely avoid the appointment of an A/E consultant and/or a PM consultant. a) True. b) False. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The LS Contract 10. The lump sum contract does not guarantee the Client the lowest possible construction cost. a) True. b) False. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The UP Contract 11. The re-measured contract is desirous to contractors since it allows a complete shifting of project risks to the Client. a) True. b) False. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT The C+ Contract 12. The cost-plus-a-fee with a guaranteed maximum contract resembles the lump sum contract in that: a) Project risks are allocated in a similar manner. b) The Client is, in a way, guaranteed an upper bound for the cost of construction. c) It gives an opportunity for the contractor to have a higher profitability. d) Any combination of the above _________. e) None of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Budget Control 13. The project’s construction budget is to be maintained by the A/E through: a) Periodic re-estimation of cost. b) Exercising good value engineering practices. c) Favoring initial cost reductions over life-cycle considerations. d) Any combination of the above: a & b. e) None of the above. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Accounting for Constructability 14. Construction expertise is “best” injected into design thinking through: a) The A/E’s acquired construction knowledge. b) The PM/CM construction background. c) Engaging the Contractor before (or soon after) the design phase starts. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Constructability? 15. Observing the issue of constructability means: a) The design can be easily constructable. b) The design can be economically constructable. c) The design drawings are deemed acceptable in terms of the level of construction details shown. d) The designer is the constructor. e) All of the above. f) Any combination of the above: a, b, & c. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT PM’s Role 16. Draft four Client-PM Agreement’s requirements describing the PM’s role in administrating the Client-A/E Agreement: 1) The PM shall closely monitor the advancement in the design progress achieved by the A/E with the aim of ensuring that all interim and final milestones are met. 2) The PM shall ensure that the A/E examine alternative design solutions leading to the selection of systems that are viable from a life-cycle costing perspective. 3) The PM shall cause the A/E to undertake periodical reviews of construction cost and review the same with the aim of maintaining the budget set by the Client. 4) The PM shall be responsible for reviewing all interim and final design deliverables for completeness and compliance with Agreement requirements. CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Engineer’s Estimate 17. If Mean-EE > 0, then: a) The Engineer might have under- priced the project b) The Engineer might have over- priced the project c) The Engineer has to revisit the design d) The Engineer has given a reasonable estimate of construction cost CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Bid Prices Distribution 18. IF Mean-Median > 0, then: a) There is a potential outlier at lower end of distribution. b) There is a potential outlier at higher end of distribution. c) The distribution may be symmetrical. d) No meaningful information can be drawn . CIVE 580 & ENMG 502 CONSTRUCTION MANAGEMENT Unbalancing 19. Bid unbalancing carried out on the basis of “a speculation on quantity” always results in bid “front- loading”: a) True. b) False. c) Not able to judge.